The biggest overall project, including Eysturoyartunnilin and Sandoyartunnlin has now come to an end. Sandoyartunnlin was open for traffic 21. December 2023, 4 months ahead of schedule.
Eysturoyartunnlin was the first tunnel to be finnish, with a total length on 11.5km. This was the first tunnel in the world with a sub-sea roundabout. Eysturoyartunnlin was open for traffic 19. December 2020, 2 months ahead of schedule. This was during the Covid-19 which affected shipment of equipment, transport etc.
Sandoyartunnlin was the largest stand-alone project ever for El-Service.
El-Service provided all the technical and safety equipment for the tunnel, which also included the SCADA Safety Control System and the Control Systems for 5 pump stations as well.
Key figures:
approx. 160km af cable lenghts
88 emergency stations with emergency phones and fire extinguishers
11 technical stations with power switchboards, etchnical equipment
5 Pummp stations
CCTV with 175 cameras, AID included.
El-Service delivered following equipment:
UPS systems, Fire Alarm Systems, speaker systems, gass and wind sensors, radion system, traffic signs, switchboards, heating detecting cable, redundant network system with fiber optic cables, A/C systems, tunnel lights, stop lights, emergency lights, barriers with our own control systems.